City of Saskatoon - Building Standards Spring 2019 Update

 Building Standards Division 

The spring construction season is around the corner and Building Standards wants to reminder customers of 2019 changes to be aware of! All information is available on the Building Standards City of Saskatoon website.

2019 Changes

Energy Compliance

Applications for new buildings and additions have to comply with either the 2017 National Energy Code for Buildings (NECB) or 2015 National Building Code (NBC) subsection 9.36. Handouts and forms have been added to the website to guide you through the application process.

Site Development Declaration (Commercial Permits)

The Site Development Declaration letter may be submitted as part of a phased or group dwelling site permit application. The letter provides confirmation that site development conforms to the initial phase permit application.  This confirmation will be used to reduce review timelines and permit application fees.

o   Site development cannot change between subsequent permit applications

o   Declaration form has to be submitted with subsequent permit applications

o   Site development is a defined term - see declaration form and handout for site development definition.

Permit Fees

New plan review fees were introduced on January 1, 2019 for building and development permit application that require review by Construction & Design and Saskatoon Water divisions. Changes to the occupancy permit fee, as well as residential permit fees also occurred January 1st. Please see Building Bylaw No. 9455 for a full list of program and service fees.

Occupancy Permits

Interim Occupancy permits are now mandatory for high risk buildings (buildings with a fire alarm system) that are intended to be occupied during construction.  If interim occupancy has not been approved, building occupancy will not be permitted and any occupancy of the building will be enforced and may result in eviction

 

Updated forms and brochures

Timelines for building and development permit applications

            Project Scope

Service Level

Type A Residential Permits

 

New Building, Addition, Alteration

5 to 7 business days

Type B Residential Permits

 

New Building

6 to 8 weeks

Additions

31 business days

Alterations

10 business days

Commercial Permits

 

New Building

5 to 10 weeks

Additions

4 to 8 weeks

Alterations

3 to 6 weeks

 

March 7, 2019